Commissioning inspections
In the commissioning inspection, Tukes assesses whether the terms set by Tukes in the permit are realised or not. With the terms, Tukes highlights the issues in legislation to which a facility must pay particular attention in its operation. The fulfilment of some terms can be confirmed before inspection or after it with e.g. documents or photos. With an on-site inspection, Tukes ensures that the facility has been constructed as planned.
Act as follows
Arrange the commissioning inspection as well in advance as possible. Your contact person in Tukes is the person who processed the permit. It is good to describe the project schedule and the estimated commissioning already in the permit application.
Below are some examples of the documents that Tukes may request for review. Find out which documents concern your operations.
Tanks, pipes and equipment:
- declaration of conformity
- declaration of conformity for the measure by the installation company
- drawings, commented versions updated
- piping and instrumentation diagrams (PI&D)
- electrical and automation drawings
- plan for the location of pressure equipment
- periodic inspection of pressure equipment
- assessing pressure equipment as a whole
- review of the tank foundations and their inspection during construction
- construction inspection
- underground inspection
EX areas:
- ventilation measurements, especially if the facility has not been classified based on it
- explosion protection document and equipment list
- ensuring the safe use of the facilities
Electrical installations:
- EX area certification inspection record
- Measurement record on earthing and equipotential bonding
Other:
- fire safety inspection record
- safety automation inspection certificate
- documentation of the alarm and fire extinguishing equipment
- maintenance plans and instructions
- operating instructions and the personnel training plan
- approving the operation supervisor for their duties
- an internal emergency rescue plan
Tukes will deliver you the inspection record within 2 months of the inspection.
Tukes assesses the system with periodic inspections.